Council for Permit Disputes annuls permit for Bioscape Antwerpen (University of Antwerp)

August 27, 2026

Environmental permit applications often refer to planned infrastructure works, such as an intersection that is due to be redesigned or a new cycling connection in the pipeline. In a judgment of 20 August 2026, the Council for Permit Disputes has now set clear limits. Anyone whose permit rests on uncertain plans may be building on quicksand.

Council for Permit Disputes annuls permit for Bioscape Antwerpen (University of Antwerp)
© Bioscape Antwerpen

The case in brief

A Belgian investment company wants to develop a new ‘Bioscape Campus’, also known as Bioscape Antwerpen, on the University of Antwerp’s Drie Eiken Campus in Edegem. The project involves a new research centre of approximately 28,000 m², comprising a single central community building of 9,987 m² and two accelerator buildings of 8,600 m² each, focused primarily on the life sciences.

On 5 September 2025, the Flemish Government, acting as the appeal authority, decided to grant a permit for the project, despite an unfavourable opinion from the Regional Environmental Permit Commission (GOVC) on, among other things, the mobility aspect. A local resident challenged the permit before the Council for Permit Disputes (RvVb).

By judgment of 20 August 2026 (No. RVVB-2526-1079), the Council annulled the permit on the ground that the mobility assessment had not been carried out with sufficient care. The Flemish Government must now take a new decision on the administrative appeal in the Bioscape file within three months.

Don’t rely on uncertain future plans

In this case, the mobility impact report (MOBER) accompanying the application found that the intersection of Drie Eikenstraat and Doornstraat already suffers from traffic problems today, and that cyclist safety there needs improvement.

Both the MOBER and the subsequent permit decision downplayed this acknowledged problem by pointing to a future redevelopment of Doornstraat and the intersection, which would supposedly improve traffic flow and increase cycling safety.

However, that redevelopment had not yet been permitted. The file did not even show that a permit application had already been submitted for these planned infrastructure works. It was therefore uncertain whether, and when, the works would be carried out.

According to the Council, the Flemish Government could not simply rely on that. A mobility assessment must be based on existing and concrete facts that have been carefully established. A future and uncertain development cannot be treated as a settled fact when it forms an essential part of the assessment.

A parking solution must also be concrete

The project also provides for 296 car parking spaces. For day to day use, the MOBER calculated a need for 288 spaces. For larger events, however, the Flemish Government acknowledged that parking capacity was insufficient.

As a possible solution, the Government pointed to an existing car park on the Drie Eiken Campus, about 300 metres from the site. However, no concrete arrangements had yet been made with the University of Antwerp on the use of this car park. The Government itself stated that this still needed to be worked out further.

According to the Council, this too was insufficient. An existing parking problem cannot be regarded as resolved simply by pointing to a solution that still has to be discussed and for which the file contains no concrete arrangements.

The practical lesson

The regulations require that a project’s mobility assessment be based on sufficiently concrete data, carefully established.

For future infrastructure works, this means above all that the more important the planned works are to the mobility assessment, the more important it is that their execution is sufficiently certain and concrete.

The same applies to solutions that depend on third parties. If a project relies on a car park, infrastructure or other measure provided by another party, for example, it must be clear that this solution will actually be available.

What does this mean for you?

For projects with a significant traffic or parking impact, it is not enough for a MOBER to refer to what might happen in the future.

You should therefore map out in good time:

• which infrastructure works are necessary for an acceptable mobility impact;

• how certain their execution is; and

• whether arrangements with third parties have actually been made and can be demonstrated in the permit file.

For permit-granting authorities, the message is that a favourable mobility assessment must be based on concrete, verifiable data, not on still-uncertain future plans.

Our Real Estate Team specialists are happy to advise you on permitting and mobility issues in real estate development.

Discover more about this topic?

I am looking for a specialist in

See more articles

Flanders Cracks Down on Substandard Housing with Significantly Higher Fines

08.09.2026

Real Estate, Renting and Co-ownership, Andersen in Belgium

Flanders Cracks Down on Substandard Housing with Significantly Higher Fines

Are you renting out a home with serious quality defects? If so, you risk criminal prosecution. Starting today, penalties for renting substandard housing in Flanders will be significantly increased. A fine can reach up to 800,000 euros under aggravating circumstances. At the same time, judges will have greater discretion to tailor the penalty to the severity of the offense.

Read the article »
Belgium transposes the Women on Boards Directive: a further step towards more balanced corporate governance

08.09.2026

Corporate Law and M&A, Andersen in Belgium

Belgium transposes the Women on Boards Directive: a further step towards more balanced corporate governance

On 18 July 2026, the Council of Ministers approved, at second reading, the preliminary draft law transposing Directive (EU) 2022/2381, better known as the Women on Boards Directive. The Directive aims to address the underrepresentation of women on the boards of listed companies and to promote equal opportunities in the appointment of directors. According to the European legislator, a balanced representation of women and men not only contributes to achieving the principle of equality, but also supports better decision-making, stronger corporate governance and greater economic competitiveness.

Read the article »
Faster Permitting Process in Brussels?

04.09.2026

Urban Planning and Environmental Law, Andersen in Belgium

Faster Permitting Process in Brussels?

The Brussels-Capital Region aims to process urban planning permits and certificates more quickly going forward. A new circular sets ambitious deadlines for Urban, the regional administration for urban planning and heritage. However, these are internal targets, not new legal deadlines. If they are not met, this will not, in itself, affect your permit or certificate application.

Read the article »
Belgium takes a first step towards digital European company law

03.09.2026

Corporate Law and M&A, Andersen in Belgium

Belgium takes a first step towards digital European company law

On 3 July 2026, the Belgian federal Council of Ministers approved a preliminary draft law which, among other things, transposes a first component of Directive (EU) 2025/25 into Belgian law. This concerns the obligation to subject the incorporation documents and amendments to the articles of association of a general partnership (VOF/SNC) or limited partnership (CommV/SComm) to prior administrative, judicial or notarial review.

Read the article »