Permit applications must be handled fairly: applicants for urban and environmental permits may not submit new technical studies or other important documents when the parties concerned are no longer able to review or comment on them in a timely manner. Yet this practice is commonplace, much to the frustration of many applicants and their legal counsels. In a judgment of 23 October 2025, the Council for Permit Disputes (CPD) now puts an end to this.

CPD 23 October 2025 (RvVb-A-2526-0131)
A project for the construction of nine single-family homes in an inner area, had previously led to three annulments by the Council for Permit Disputes. In the fourth round, just before the hearing at the Provincial Authority, the applicant submitted an additional noise study and a report on odor nuisance. These very documents ultimately proved decisive for the Provincial Authority to grant a permit.
This caused great dissatisfaction for the appellant, who was unable to examine these new documents in time and felt blindsided. According to the appellant, the Provincial Authority should have investigated whether these late submissions required a new public consultation or should have been submitted again to the provincial planning officer. Aggrieved by this procedure, the appellant lodged an appeal with the Council for Permit Disputes.
The Council reminded that, although it is possible to submit new documents during an appeal, certain conditions must be met (cf. Article 64 of the Environment Permit Decree). One of these conditions is that the rights of third parties are not infringed, such as the right to defend themselves in a useful and informed manner.
According to the Council, the new studies were by no means incidental. That the appellant only saw them for the first time during the hearing was a step too far for the Council: the public must not be confronted with faits accomplis. Therefore, the permit could not rely on information of which the appellant could not take timely notice, let alone comment on – certainly not without any justification provided by the Provincial Authority. The permit was therefore annulled.
The key lesson from this ruling is simple yet fundamental for any permit procedure: transparency and timeliness are not mere formalities, but basic conditions for a fair process. Applicants cannot “fix” their file by suddenly submitting additional studies at the last minute, and permitting authorities may not simply accept such documents.
The Council thus clearly draws a line against the practice of last-minute file corrections to the detriment of appellants against an environment permit. For applicants, this means that essential documents should be submitted in a timely manner, while authorities must ensure that any changes are properly assessed in accordance with Article 64 of the Environment Permit Decree (with justification). This prevents a permit from being annulled at a later stage.
Do not hesitate to contact Andersen’s Real Estate team in Belgium for more information and assistance in proceedings before the Council for Permit Disputes and other administrative courts.
Matias Osorio Olivera (Counsel)
I am looking for a specialist in

14.01.2026
•Real Estate, Renting and Co-ownership
By judgment of 18 December 2025, the Belgian Court of Cassation delivered a significant ruling in a disciplinary (disciplinary law / professional disciplinary proceedings) case against a real estate agent, with far-reaching consequences for the real estate profession.

13.01.2026
•Real Estate, Renting and Co-ownership
In an important judgment of 19 December 2025 (C.25.0192.F), the Court of Cassation emphasized the fundamental importance of the architect’s duty of supervision when selecting the contractor, in particular with regard to the contractor’s access to the profession.

13.01.2026
•Commercial and Economic Law
With Book 9 of the Civil Code, the autonomous guarantee - also known as a bank guarantee or guarantee on first demand - now has, for the first time, a clear statutory basis in Belgium. Until now, this legal instrument was primarily shaped by case law, customary practice, and international soft law. With regard to the latter, reference is often made to the so-called URDG 758 (Uniform Rules for Demand Guarantees), a set of practical rules drawn up by the International Chamber of Commerce (ICC). These rules are not binding as such, but they are frequently used in (inter)national trade because they provide uniform and recognizable arrangements and thus legal certainty.

08.01.2026
•Sustainability
In an ideal world, every company operates sustainably, every company produces in a CO₂-neutral way, every company respects human rights throughout its value chain, and every company is fully transparent about its sustainability impact on its direct and indirect environment. Companies generate strong profits, and shareholders are satisfied stakeholders who share in these generous returns.