When a developer suffers loss because works have been carried out defectively, the following question regularly comes up: may the developer, in addition to claiming damages, also refuse to pay (part of) the contract price? The Belgian Court of Cassation recently examined this point in a ruling of November 8, 2024. The ruling re-affirms fundamental principles of the law of damages and has significant consequences for the day-to-day practice of construction contracts.
A contractor was engaged to carry out a building project for an agreed contract price of almost €300,000. The developer later discovered defects, including a leaking roof and an inadequate concrete floor, and therefore refused to pay the outstanding balance of approximately €29,348.22.
The court of first instance held that the developer was entitled to damages of €19,579.04 and at the same time rejected the contractor’s claim for payment of the invoice balance. The Antwerp Court of Appeal confirmed that decision.
The contractor brought the case before the Court of Cassation, arguing that refusing to pay the invoice and awarding damages amounted to double compensation for the same loss, thereby breaching the principle of full (but not excessive) compensation.
The Court of Cassation quashed the Antwerp judgment. It accepted the contractor’s argument and found that the appellate court had awarded the developer more than the actual loss suffered, thus infringing Article 1149 of the former Civil Code.
Under the principle of full compensation a debtor must make good the loss resulting from a faulty non-performance of a contractual obligation. That loss includes both actual loss and loss of profit and should place the creditor in the position he would have been in had the obligation been properly performed.
Where a contractor performs defectively, the developer may therefore in principle claim full compensation for the loss sustained.
Crucially, the Court re-affirmed that a creditor may not at the same time:
Such cumulation would amount to double compensation and therefore to over-compensation, contrary to the principle of full reparation.
A developer faced with defective works may not both refuse to pay the outstanding contract price and claim damages for those very defects, unless he strictly applies the correct legal basis:
If the defects do not justify termination, the developer can also claim a price reduction. A price reduction adjusts the contractual balance and is distinct from damages; it cannot normally be combined with other compensatory measures.
With its judgment of 8 November 2024 the Court of Cassation puts an end to lingering uncertainty about the reciprocal rights and duties arising from defective performance in construction contracts.
The ruling upholds the logic of contractual balance: loss must be made good fully, but no more than fully. Contractors keep their right to be paid for work done, even when liable for defects—so long as that payment does not conflict with a properly established compensation or price reduction.
For developers and contractors alike this means: draft clear contracts, apply the rules on compensation correctly, and above all avoid pursuing “double recovery” before the courts.
Do you have questions regarding the application of these new rules? Our team is ready to support and advise you.
I am looking for a specialist in
18.06.2025
•Real Estate, Renting and Co-ownership
On March 28, 2025, the Belgian Supreme Court clarified how the expiration period must be calculated for a tenant seeking eviction compensation when a commercial lease is not renewed.
23.05.2025
•Employment Law
Among all OECD countries, Belgium has the highest tax burden on labour. Nevertheless, in order to attract qualified personnel from abroad, Belgium has long provided a favourable expatriate tax regime. This regime is designed to ease the substantial Belgian tax and social security pressure for expatriates. In 2022, a new expatriate tax regime was introduced, although it is generally considered to be less advantageous than the previous system. The so-called Easter Agreement introduces a number of measures aimed at making the current regime more attractive again.
22.05.2025
•Employment Law
The National Labour Council has recently carried out a comprehensive revision of Collective Labour Agreement No. 32bis of 7 June 1985 (“CLA No. 32bis”). The update aims to strengthen the obligations regarding the information and consultation of employees in the event of a transfer of undertaking.
15.05.2025
•Tax Law
As of January 1, 2025, new legislation has come into force aimed at simplifying and optimizing the VAT chain (the mechanism by which VAT is collected and deductible at each stage of the supply of goods or services to an end user).