When a developer suffers loss because works have been carried out defectively, the following question regularly comes up: may the developer, in addition to claiming damages, also refuse to pay (part of) the contract price? The Belgian Court of Cassation recently examined this point in a ruling of November 8, 2024. The ruling re-affirms fundamental principles of the law of damages and has significant consequences for the day-to-day practice of construction contracts.

A contractor was engaged to carry out a building project for an agreed contract price of almost €300,000. The developer later discovered defects, including a leaking roof and an inadequate concrete floor, and therefore refused to pay the outstanding balance of approximately €29,348.22.
The court of first instance held that the developer was entitled to damages of €19,579.04 and at the same time rejected the contractor’s claim for payment of the invoice balance. The Antwerp Court of Appeal confirmed that decision.
The contractor brought the case before the Court of Cassation, arguing that refusing to pay the invoice and awarding damages amounted to double compensation for the same loss, thereby breaching the principle of full (but not excessive) compensation.
The Court of Cassation quashed the Antwerp judgment. It accepted the contractor’s argument and found that the appellate court had awarded the developer more than the actual loss suffered, thus infringing Article 1149 of the former Civil Code.
Under the principle of full compensation a debtor must make good the loss resulting from a faulty non-performance of a contractual obligation. That loss includes both actual loss and loss of profit and should place the creditor in the position he would have been in had the obligation been properly performed.
Where a contractor performs defectively, the developer may therefore in principle claim full compensation for the loss sustained.
Crucially, the Court re-affirmed that a creditor may not at the same time:
Such cumulation would amount to double compensation and therefore to over-compensation, contrary to the principle of full reparation.
A developer faced with defective works may not both refuse to pay the outstanding contract price and claim damages for those very defects, unless he strictly applies the correct legal basis:
If the defects do not justify termination, the developer can also claim a price reduction. A price reduction adjusts the contractual balance and is distinct from damages; it cannot normally be combined with other compensatory measures.
With its judgment of 8 November 2024 the Court of Cassation puts an end to lingering uncertainty about the reciprocal rights and duties arising from defective performance in construction contracts.
The ruling upholds the logic of contractual balance: loss must be made good fully, but no more than fully. Contractors keep their right to be paid for work done, even when liable for defects—so long as that payment does not conflict with a properly established compensation or price reduction.
For developers and contractors alike this means: draft clear contracts, apply the rules on compensation correctly, and above all avoid pursuing “double recovery” before the courts.
Do you have questions regarding the application of these new rules? Our team is ready to support and advise you.
I am looking for a specialist in

12.11.2025
•Urban Planning and Environmental Law
The Council for Permit Disputes (RvVb) confirms that permanent residence is not a requirement for inclusion as a dwelling in the permit register. It is sufficient that the construction is primarily intended for residential use. A request for inclusion in the permit register may therefore not be refused on the grounds that permanent residence has not been demonstrated.

07.11.2025
•Urban Planning and Environmental Law
The Council for Permit Disputes (RvVb) annulled, on 9 October 2025, a financial charge imposed in a decision granting an environmental permit. Such a charge may, since 2024, only be imposed on the basis of an urban planning regulation within the meaning of Articles 2.3.1 and 2.3.2 of the Flemish Code for Spatial Planning (VCRO). Prior to the amendment of the Decree, the Environmental Permit Decree did provide that such a financial charge could be imposed by the permitting authority and under what conditions, but it was not required that a regulation be included in an urban planning ordinance.

06.11.2025
•Administrative Law and Public Procurement
Local authorities face a dilemma: they want to invest in public construction projects, but are no longer allowed to assess their own projects when these have a significant impact on the environment. A new draft decree aims to break the deadlock, but at the same time raises questions about how independent the assessment will really be when it is simply shifted to another political level.

04.11.2025
•Administrative Law and Public Procurement
On October 23, 2025, the new European threshold amounts that tighten public procurement regulations were published in the European Official Journal. When awarding public procurements, the contracting authority must take into account a number of threshold amounts.